Technical Reviews. MarkClaussen reported that the regular, large, and triggered proposal reviews for the VLA/VLBA/GMVA are completed and have been vetted. The plan is for the technical reviews for the X-proposals, being reviewed by MarkClaussen and AmyMioduszewski, to be completed by COB on Friday. DanaBalser reported that the GBT reviews are done but have not all been vetted yet by ToneyMinter. He should complete these by the end of the weekend.
Science Reviews. DanaBalser reported that the deadline for Individual reviews was delayed for 4 of the 9 SRPs since their telecons begin during the second telecon week. Thus far no SRPs have completed their reviews which are nominally due today COB.
SRP Telecons. We confirmed that DanaBalser and AmyMioduszewski will swap support for the EGS and SSP second telecon windows. JessicaUtley will update the telecon schedule. DanaBalser will update the intro and gender info that are presented at the start of each SRP telecon.
PST Review Items. All PST 20A review items were completed and released earlier. No additional work is planned for 20A.
PHT Review Items. RickLively reported that six tickets have been prioritized for 20A by AmyMioduszewski et al. The top two tickets concern issues with the Any configuration time. The plan is for RickLively to work on these and if time permits move down the list.
X-Proposals. DanaBalser reported that the detailed schedule is still in flux. The initial assessment will consist of a technical reviews and a course scientific evaluation (excellent, good, fair, poor), plus text with the strength and weakenesses. He will put this info on the secure wiki page.