NRAO Interactive Services Plan of Record

October 2010 Cycle

Interactive Services includes http://my.nrao.edu, proposal submission, proposal handling, analytics, administration, and the CASA beta helpdesk.

Weeks

  • Weeks 1-3
  • Weeks 4-6
  • Weeks 7-9
  • Weeks 10-12

Target release dates for PST Enhancements (must be vetted by Open Sky):

DateAction
30 June 2010Review plan of record.
05 July 2010Finalize plan of record.
03 September 2010Release Candidate available for acceptance testing.
17 September 2010Release of PST.
17-24 September 2010Updates at 9pm CT based on initial feedback.

Key for the "Task Status" column:

  • DONE (%Y%) means the task has been successfully completed
  • MOVED TO... (%M%) means the task has been completed and is awaiting integration tests
  • PICK (%S%) means the task has been completed and is awaiting sponsor tests
  • ALERT! (%X%) means the task will not be completed this cycle, but was expected to be completed
  • ok means that the task is not yet complete or ready for tests, but Nicole and/or Dana have evaluated results & progress is clearly on track

Key for the "MR Status" column:

  • DONE (%Y%) means the MR has final sponsor sign-off
  • MOVED TO... (%M%) means the MR is awaiting final sponsor sign-off
  • PICK (%S%) means the MR is being implemented
  • REFACTOR (%P%) means the MR is either being written, checked, or needs initial sponsor approval
  • N/A means there is no MR for this task

1. Operational/User Support Items Completed During This Cycle

For each support item, please list the amount of effort involved as either: low, medium, or high. Guidelines for these rankings are as follows:
  • low - Things that take less than two hours.
  • medium - Things that take more than two hours, but less than eight hours.
  • high - Things that take more than eight hours.

If multiple people are involved in an item, please list it only once. Effort estimates should reflect total time elapsed, i.e. how long did it take to fix the problem start to finish - not the sum total of each person's time.

Requested Date Target Date Completed Date People Work Description


2. Commitments

The default/unsorted state reflects priority order for this cycle.

As MRs are completed and additional details are available on each task, Open Sky should comment regarding which elements can be fit into a 4-week development period, and which should be migrated down to Background Tasks.

Project Task Info/MR Lead Sponsor, Team Notes Status text
Proposal Submission Tool
EVLA/VLBA/GBT Resources
 
 
 
Proposal Submission Tool
Misc.
 
 
 
Interactive Services
Data Processing Tab
 
 
 


3. Background Tasks

Things to do if we get time for them.

Project Task Info/MR Lead Sponsor, Team Notes Status text


4. Other Maintenance & Enhancements

Description Tests Submitter Notes Status

-- DanaBalser - 2010-06-28

This topic: Software > ProposalSubmissionTool > IntxSvcsPlanOfRecordT22010
Topic revision: 2010-06-30, DanaBalser