EVLA/VLBA/GBT Resources
NRAO Interactive Services Modification Request 1 T2 2010
1. Introduction
Any changes to the telescope specific resources
2. Background
3. Requirements
- EVLA - the following changes
- Add 4-band 400cm receiver and add a pop-up message when it was selected saying something like: "Bandwidth for 74 MHz is currently under test."
- VLBA - maybe some minor changes.
- GBT - the following changes:
- MUSTANG
- Add a parameter that selects either "MUSTANG64" or "MUSTANG100 (Shared Risk)".
- Change the text to:
- MUSTANG64 is a bolometer array with 64 pixels operating with a 18 GHz bandwidth centered at 90 GHz. MUSTANG100 is functionally equivalent to MUSTANG64 except with 100 pixels, a predicted sqrt(2) better sensitivity, and a slightly smaller field of view (35 arcsec instead of 42 arcsec). *MUSTANG100 is shared risk and should only be selected if the higher sensitivity is necessary. Please contact Brian Mason (bmason@nrao.edu) for more details and collaboration information.
- KFPA
- Removed "Shared Risk".
- Change https://safe.nrao.edu/wiki/bin/view/KPAF/2010Call to https://safe.nrao.edu/wiki/bin/view/KPAF/2011Call.
- Add the following modes:
- 1 beam, 4 spectral windows, 2 polarization, at either 12.5 MHz or 50 MHz bandwidth
- 1 beam, 4 spectral windows, 2 polarization, at either 200 MHz or 800 MHz bandwidth
- 2 beam, 4 spectral windows, 2 polarization, at either 12.5 MHz or 50 MHz bandwidth
- 2 beam, 2 spectral windows, 2 polarization, at either 200 MHz or 800 MHz bandwidth
4. Design
Technical lead should provide a brief description of how this will be implemented in the code.
5. Deployment Checklist
Documentation? Systems/hardware/networking things needed for deployment?
6. Test Plan
6.1 Internal Testing
6.3 Integration/Regression Tests
Signatures
APPROVED: I acknowledge that my request is fully contained in this MR, and if the Open Sky (or other NIS or PST developers) deliver exactly what I specified, I will be happy.
ACCEPTED: I acknowledge that I have validated the completed code according to the acceptance tests, and I am happy with the results.
Written |
- - - - - |
Checked |
- - - - - |
Approved by Scientific Sponsor |
- - - - - |
Accepted/Delivered by Sponsor |
- - - - - |
Symbols:
- Use
%X%
if MR is not complete (will display
)
- Use
%Y%
if MR iscomplete (will display
)
Discussion Area
--
DanaBalser - 2010-06-28