In accordance with the recommendations of Eduardo Miranda's consultation, projects are defined as efforts that require more than 3 people or are expected to consume more than 2 weeks of effort. All projects should divide the requirements / features into "Must Haves", "Should Have", and "Could Have" levels. The time estimate for the project should be set such that under worst case the "Must Haves" can be completed. Test and validation plans are expected to be completed prior to the review stage.
-- JeffKern - 2015-10-02