SRDP Conceptual Design Review

  • Date: May 10-11, 2018
  • Location: NRAO Headquarters, Edgemont Road

Review Report

Note: The review plan is included in the Review Report.

Review Documents

Documents marked with recentchanges have been modified after review in response to the committees recommendations.

SRDP Project Documents

Project Management

System Engineering

Stakeholder Requirements and Captured L2 Requirements

Data Management and Software Documents


Review Logistics

  • Contact Information for Remote Participants:

Agenda

Time Topic Lead Presenter
May 10
8:30   Executive Session Berriman
9:00   Introduction and Welcome Beasley
9:15 ppt Context Kern
10:30 Coffee
10:45 ppt Requirements Kern
12:30 Lunch
13:30 ppt Cost Model Kern
15:15 Coffee
15:30 ppt Implementation Griffith/ Kern
16:15 ppt Quality Kern
16:45   Open Issues All
17:00   Executive Session Berriman
18:30 Dinner at Burton's Grill
May 11
8:30 ppt Architecture Hiriart
9:00   Topics from the Committee Berriman
9:30   Executive Session Berriman
11:30   Initial Findings and Closeout Berriman
12:30 Lunch
-- JeffKern - 2018-03-22

This topic: SRDP > WebHome > ConceptualDesignReview
Topic revision: 2018-07-02, JeffKern
This site is powered by FoswikiCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding NRAO Public Wiki? Send feedback