USNO VLBA Support Meeting

December 12, 2013 Time 11 am Mountain, 1pm Eastern

575-835-7170

USNO: Nicole, Dave, Chris, Alan, Dan, John

NRAO: Walter, Ephraim, Craig, Steven

Agenda:

Previous Action items:
  • Correlator:
    • James Robnett visit to USNO (late january 2014) with Mike Hatz (NRAO-CV)
    • James will provide a full parts list - Done
    • Status of as-built drawings - carry over, network diagrams being done.
Status
  • Correlator:
    • Status of Phase 2
      • All the orders have been placed for Phase II + Lustre install. Some items have begun arriving and James expects all items to be there by the first week of January.

      • 2 racks arrived, cables & cords have arrived.

      • Nicole is keeping James informed as items arrived

    • Other: None.
  • MK/PT Status
    • Prospects for extending Internet contract support through FY14 - set through July.
    • Daily observations support contracts ends in January 2014.
      • Extension signed recently for 500k recently at USNO, but not seen in NRAO.
    • Discussion of streamlining data delivery from backup VLBA intensives
      • Walter: will find someone with engineering to head up. Will deal with correct data flow and ease operations impact. Background: data sent on solid state drives, mailed from sites to USNO.
      • Action USNO: verify receipt of SSD external fine, provide address and POC.
    • Investigate the addition of another 2 VLBA antennas for new series of 4-antenna USNO observations.
      • Not scheduled, goal to begin is as soon as possible.
      • take a key file, add 2 new antennas and let SCHED optimize for all 4.
      • Action NRAO: who is POC for 4-antenna observation effort? (Jon?)
  • Daily Observation Report.
    • 3 days had issues but the backup "b" observations were used.
    • PT had generator/power/FRM issues at the end of November. Los Alamos was used instead.
  • Open issues
    • Jon Romney will likely lead the UTC-UT1 observation effort.
      • Action NRAO (Steve): Confirm?
      • UT1 mailing list is still avenue to communicate through
      • POC makes sure daily log and report are copied.
    • Nicole - still will follow-up on previous networking question.
    • Next meeting January 9th, 2014.
-- EphraimFord - 2013-12-10