-- StevenWhite - 2009-11-20

Schedule

Receiver Testing

Task Description Date Started Date Complete Responsible Check
M&C Tests
Functional Tests
23 November 2009
30 November 2009
M. Whitehead P. Brandt
DONE
Setup Hardware for Tests.
Set HEMT Bias ; IDM. Temp. HEMT
7 December 2009
15 December 2009
B. Simon G. Watts S.White
DONE
Back Plane layout
Correct Backplane
10 December 2009
15 December 2009
G. Watts C.Niday
DONE
Receive and Populate Backplane
Vendor manufacture and NRAO wire
29 December 2009
15 January 2009
G. Watts C.Niday K.Ward
DONE
Pump Down
Vacuum Check and Pump Down
16 December 2009
21 December 2009
B. Simon B. Simmons
DONE
Cold Plate Replace
New Copper Plate
04 January 2010
6 July 2010
B. Simon
DONE
Cool Down
Corrections Solved Problem
8 January 2010
15 January 2010
B. Simon G.Watts M. Whitehead P. Brandt
DONE
Cold Gain Tests
Check Gain
18 January 2010
19 January 2010
B. Simon
DONE
Noise Temperature Tests
Noise Temperature Tests
19 January 2010
20 January 2010
B. Simon E. Bryerton M. Morgan
DONE
Gain Modulation and Stability Tests
Finalize Stability with Telescope Preparation
20 January 2010
21 January 2010
B. Simon R. Norrod
DONE
LO Stability Tests
Tests with Modified Doubler
22 February 2010
5 March 2010
B. Simon S. White
DONE
Install 8 way Splitter (Commercial)
MCI designed Splitter
23 March 2010
25 March 2010
K. Ward
DONE
GBT Installation
Install the Engineering & Software Tests
9 March 2010
9 March 2010
S. White G. Langston B. Simon
DONE
Engineering and Software Tests
M&C, Balance, Spectrometer,Spurious,Stability
9 March 2010
23 March 2010
G. Langston, S. White
DONE
Continuum Gain Checks
Three freq. continuum obs. all beams.
31 March 2010
8 April 2010
G. Langston, S. White, D. Frayer
DONE
IF Spur search
band scan, all beams 15 min/200MHz
31 March 2010
8 April 2010
G. Langston
DONE
Spectral Satability
Selected bands, 1 hour/frequency
8 April 2010
15 April 2010
G. Langston, S. White
DONE
Mapping tests
1/4 deg. maps, FS/PS + Cal/NoCal
15 April 2010
22 April 2010
G. Langston, B. Garwood, J. Masters
DONE
Large Map test
1 deg map, Optimized map
22 April 2010
4 May 2010
B. Garwood, J. Masters, G. Langston
DONE

Gantt Chart for Testing Schedule

Topic revision: r26 - 2010-08-26, StevenWhite