Project Charter
Observations in the K-band frequency spectrum (18-26.5 GHz) of extended sources in the spectral line require inordinate amounts of telescope time with a single pixel receiver. Focal-plane array instruments improve telescope efficiency with additional sampling of the aperture plane. A seven beam K-band instrument will be developed that improves mapping speed and map calibration for extended molecular regions, and provides a costing model for future focal-plane array projects. The funding of the project is through Lockheed Martin funds which includes a contingency for beginning work on spectrometer development and data transmission, or for funding personnel in case of schedule slippages.
Project Deliverables
- A dual circular polarized seven beam K-band receiver with up to 1.8 GHz of instantaneous bandwidth.
- Software for monitor and control, configuration support, and data analysis.
- A documented design and costing model per pixel for expansion of the instrument.
Project Scope
In three years an instrument for improved spectral line mapping at K-band is delivered. Although the feeds are uncooled, all components preceding and including the HEMT amplifiers are cooled providing low system temperature for efficient mapping. Calibration is by a cooled noise injection module. A tunable downconverter multiplexes two fixed polarizations onto a single channel compatible with the existing GBT IF system and spectrometer. A data analysis package will aid in instrument commissioning and provide methods for generating maps from the collected data.
Outside the scope are:
- A new spectrometer and data transmission system.
- An efficient and extensive data reduction package.
- Increased data storage and archiving capabilities.
Communications Plan
- A monthly meeting with team members.
- Weekly progress at Friday Commissioning Meetings.
- Conceptual Design Review to finalize the design (~1/08).
- Critical Design Review for single pixel results disclosure (~08/08).
- Periodic reports to Users Committee.
- Monthly updates sent to email list.
- NRAO newsletters updates.
- NRAO-GB instrumentation brochures status report.
- Poster presentations or talks at SPIE, or other similar conferences.
Stakeholders
- User Committee
- Science Advisory Committee
- The general users community and news letter recipients.
- Fred Lo, NRAO Director
- Phil Jewel, NRAO Associate Director
- Karen O'Neil, GB Site Director
- Jay Lockman, Project Scientist
- Glen Langston, Scientist
- Steve White, Project Manager
- Matt Morgan, Project Engineer
- Eric Bryerton, Engineer
- Kamaljeet Saini, Engineer
- Roger Norrod, Engineer
- Bob Simon, Engineer
- Gary Anderson, Engineer
- Sivasankaran Srikanth, Engineer
- Dennis Egan, Engineer
Project Charter Approval
- Approved by PTCS Team Members
-
Steve White
-
Jay Lockman
-
Matt Morgan
-
Eric Bryerton
-
Kamaljeet Saini
-
Sivasankaran Srikanth
-
Roger Norrod
-
Bob Simon
-
Gary Anderson
-
Dennis Egan
- Approved by GBT Program Management
-
Karen O'Neil
-
Richard Prestage
Symbols:
- Use
%X% not approve (will display
)
- Use
%Y% approve (will display
)
2009AugustJDEcost.pdf Details of Labor Cost as of August 2009.
LM050expenditures2009_Cum.pdf Details of Parts Cost as of August 2009.
LM050expenditures2009.xls Details of expenditures as of March 2009.
Year 1 Effort Requests details responsibilities and efforts for the first year.
Year 2 Effort Requests details responsibilities and efforts for the second year.
Year 3 Effort Requests details responsibilities and efforts for the third year.
The
Work Breakdown Structure for the project.
This
networkdiagram is a diagram for development and construction, which details the interrelations.
A MS Project
KFPAGanttupdateJuly2009.mpp: July 2009 update.
Estimated costs for a seven feed K band focal plane array:
CostEstimate7feed.pdf
MS Excel file containing the tables for both labor estimates and cost estimates:
Excel File
Project Milestones
| Target Date |
Deliverable |
Complete |
Lead |
| 01/15/08 |
System Design Complete with Conceptual Design Review acceptance. |
|
| 08/13/08 |
M&C Hardware Module with support software complete. |
|
| 08/22/08 |
Single Pixel Construction Complete |
|
| 08/31/08 |
Single Pixel Receiver Laboratory Characterization and Measurement. |
|
| 10/30/08 |
Single Pixel Receiver Telescope Commissioning Complete |
|
| 02/06/09 |
Critical Design Review Acceptance. |
|
| 08/01/09 |
Monitor and Control Hardware Delivered. |
|
| 08/15/09 |
Noise Module Delivered. |
|
| 09/01/09 |
Monitor and Control Hardware Delivered. |
|
| 09/07/09 |
Monitor and Control Software Tested with Hardware. |
|
| 09/07/09 |
Integrated Down Converter Module Delivered. |
|
| 10/13/09 |
Observing Support Status MR Status |
|
Mark,Patrick,Steve,Glen |
| 11/13/09 |
Multi-pixel Construction complete. |
|
Bob Simon |
| 01/25/10 |
System Integrate & LAB Test complete(without doubler). |
|
Bob Simon |
| 03/16/10 |
System Integrate & LAB Test complete(with doubler). |
|
Bob Simon |
| 03/31/10 |
Telescope Engineering Test Complete |
|
Steve, Bob, Glen |
| 11/08/10 |
Commissioning complete. |
|
Glen |
Seven Pixel Schedule
Pipeline Specific Milestones
| Target Date |
Deliverable |
Document/Link |
Lead |
| 09-11-18 |
Weather-based calibration scalars to SDFITS output (tau-zenith and T-atm) document |
MR-23C509 |
Bob |
| 09-11-18 |
Rest frequencies to GO FITS file to be used by SDFITS |
MR-1Q110 |
Bob |
| 09-12-01 |
Tracking the RA, Dec of the selected beam in multi-beam feed systems |
MR-3C608 |
Bob |
| 09-12-15 |
Weather-based calibration scalars to SDFITS output (tau-zenith and Tatm) complete |
MR-23C509 |
Bob |
| 09-11-25 |
AIPS imaging callable from IDL document |
MR-? |
Glen |
| 09-12-15 |
Define image cube output frequency definition (interpolation etc) |
MR-? |
Jay |
| 10-01-15 |
AIPS imaging callable from IDL complete |
MR-? |
Bob |
| 10-01-15 |
Prototype pipeline implemented |
|
Bob/Joe |
| 10-01-15 |
Scal/vector calibration methods |
|
Ron/Frank |
| 10-01-15 |
Scal/vector calibration use documentation |
|
Glen |
| 10-03-01 |
Pipeline Prototype Internal Review |
|
Glen |
| 10-03-15 |
Full Pipeline Development Plan Circulated |
|
Glen |
| 10-05-15 |
Pipeline v1.0 (python, with some real-time features) delivered |
|
Bob/Joe |
| 10-08-15 |
Pipeline external review |
|
Glen |