-- StevenWhite - 2010-03-31

LO Development Milestones

TaskSorted ascending Description Date Started Date Complete Signed Check
Amplifier Assembly
Assemble parts, substrate, carrier
21 October 2009
20 November 2009
 
ALERT!
Amplifier Carrier Modification
Modified and Sent for Gold Plate ~50%
8 June 2009
18 December 2009
S. White
DONE
Amplifier Design
Amplifier Bias Design
24 April 2009
2 October 2009
S. White
DONE
Amplifier Substrates
Receive Substrates from Vendor
24 April 2009
2 October 2009
S. White
DONE
Amplifier Tests
Test and Delivery
26 October 2009
20 November 2009
 
ALERT!
Design Doubler
MMIC X 2
24 April 2009
2 October 2009
S. White
DONE
Double Carrier Modification
Carrier for PCB Modified and Sent for Gold Plate ~50%
27 March 2009
18 December 2009
S. White
DONE
Doubler PreTests
Laboratory Measurements
2 February 2009
24 April 2009
S. White
DONE
Doubler Assembly
Assemble parts, substrate, carrier
23 October 2009
18 December 2009
 
ALERT!
Doubler Substrates
Receive Substrates from Vendor
27 March 2009
2 October 2009
S. White
DONE
Doubler Tests
Test and Delivery
26 October 2009
20 November 2009
 
ALERT!
Equalizer Assembly
Assemble parts, substrate, carrier
26 Oct 2009
20 November 2009
 
ALERT!
Equalizer Carrier Modification
odified and Sent for Gold Plate ~50%
8 June 2009
18 December 2009
S. White
DONE
Equalizer Desgin
Equalizer Model Substrate
24 April 2009
5 October 2009
S. White
DONE
Equalizer Substrate
Receive Substrates from Vendor
02 Oct 2009
23 October 2009
S. White
DONE
Equalizer Test
Test and Delivery
2 Nov 2009
20 November 2009
 
ALERT!
Filter Assembly
Assemble parts, substrate, carrier
21 Oct 2009
11 December 2009
 
ALERT!
Filter Carrier Modification
odified and Sent for Gold Plate
05 Oct 2009
16 October 2009
S. White
DONE
Filter Design
Filter Model
24 April 2009
2 October 2009
S. White
DONE
Filter Substrate
Receive Substrates from Vendor
05 Oct 2009
16 October 2009
S. White
DONE
Filter Tests
Test and Delivery
26 October 2009
21 October 2009
 
ALERT!
Splitter Assembly
Assemble and Bond 75%
21 October 2009
11 December 2009
 
ALERT!
Splitter Carrier Modification
Modified and Sent for Gold Plate ~%50
2 October 2009
18 December 2009
S. White
DONE
Splitter Design
Wilkenson Design
8 June 2009
2 October 2009
S. White
DONE
Splitter Substrate
PCB from Vendor
8 June 2009
2 October 2009
S. White
DONE
Splitter Tests
Test and Delivery
26 October 2009
20 November 2009
 
ALERT!
Test Filter
Characterization of Original Design
16 March 2009
24 April 2009
S. White
DONE

Topic revision: r1 - 2010-03-31, StevenWhite