| Task | Description | Date Started | Date Complete | Signed | Check |
|---|---|---|---|---|---|
| Doubler PreTests |
Laboratory Measurements |
2 February 2009 |
24 April 2009 |
S. White |
|
| Test Filter |
Characterization of Original Design |
16 March 2009 |
24 April 2009 |
S. White |
|
| Design Doubler |
MMIC X 2 |
24 April 2009 |
2 October 2009 |
S. White |
|
| Doubler Substrates |
Receive Substrates from Vendor |
27 March 2009 |
2 October 2009 |
S. White |
|
| Double Carrier Modification |
Carrier for PCB Modified and Sent for Gold Plate ~50% |
27 March 2009 |
18 December 2009 |
S. White |
|
| Doubler Assembly |
Assemble parts, substrate, carrier |
23 October 2009 |
18 December 2009 |
|
|
| Doubler Tests |
Test and Delivery |
26 October 2009 |
20 November 2009 |
|
|
| Amplifier Design |
Amplifier Bias Design |
24 April 2009 |
2 October 2009 |
S. White |
|
| Amplifier Substrates |
Receive Substrates from Vendor |
24 April 2009 |
2 October 2009 |
S. White |
|
| Amplifier Carrier Modification |
Modified and Sent for Gold Plate ~50% |
8 June 2009 |
18 December 2009 |
S. White |
|
| Amplifier Assembly |
Assemble parts, substrate, carrier |
21 October 2009 |
20 November 2009 |
|
|
| Amplifier Tests |
Test and Delivery |
26 October 2009 |
20 November 2009 |
|
|
| Filter Design |
Filter Model |
24 April 2009 |
2 October 2009 |
S. White |
|
| Filter Substrate |
Receive Substrates from Vendor |
05 Oct 2009 |
16 October 2009 |
S. White |
|
| Filter Carrier Modification |
odified and Sent for Gold Plate |
05 Oct 2009 |
16 October 2009 |
S. White |
|
| Filter Assembly |
Assemble parts, substrate, carrier |
21 Oct 2009 |
11 December 2009 |
|
|
| Filter Tests |
Test and Delivery |
26 October 2009 |
21 October 2009 |
|
|
| Equalizer Desgin |
Equalizer Model Substrate |
24 April 2009 |
5 October 2009 |
S. White |
|
| Equalizer Carrier Modification |
odified and Sent for Gold Plate ~50% |
8 June 2009 |
18 December 2009 |
S. White |
|
| Equalizer Substrate |
Receive Substrates from Vendor |
02 Oct 2009 |
23 October 2009 |
S. White |
|
| Equalizer Assembly |
Assemble parts, substrate, carrier |
26 Oct 2009 |
20 November 2009 |
|
|
| Equalizer Test |
Test and Delivery |
2 Nov 2009 |
20 November 2009 |
|
|
| Splitter Design |
Wilkenson Design |
8 June 2009 |
2 October 2009 |
S. White |
|
| Splitter Substrate |
PCB from Vendor |
8 June 2009 |
2 October 2009 |
S. White |
|
| Splitter Carrier Modification |
Modified and Sent for Gold Plate ~%50 |
2 October 2009 |
18 December 2009 |
S. White |
|
| Splitter Assembly |
Assemble and Bond 75% |
21 October 2009 |
11 December 2009 |
|
|
| Splitter Tests |
Test and Delivery |
26 October 2009 |
20 November 2009 |
|
|