KFPA Automatic Balance of IF path
Modification Request #? (C04 2009)
1. Introduction
The basic observing modes for the KFPA are similar to those already used by spectral line observers.
This document specifies the automatic balancing of the IF path for optimum signal levels
input to the spectrometer.
2. Background
We have described KPFA pointing and focus plans for commissioning
previously.
The effective use of these procedures require optimum input levels to the back end
and also through the fiber chain.
3. Requirements
The configuration tool will be modified so that all the IF paths (7 beams each with
two polarizations) will have near optimum signal levels.
4. Design
Each amplifier in the GBT RF/IF chain has an optimum input signal level that
allows accommodation of changes in the system temperature changes. An additional
constraint for the 7 feed system is that two polarizations will be transmitted
on a single fiber, so the RF design must accommodate this by providing similar
signal levels on the two polarizations to the fiber.
5. Example Usage
The balance function has few arguments, if any.
6. Deployment Checklist
Steps in the deployment checklist.
7. Test Plan
7.1 Internal Testing
The software group must fill out this section
This section covers things like unit testing, simulator testing, and any other tests required to make sure this MR is ready for sponsor/integration/regression testing.
The sponsor testing for the balance function will be done with the input signal
levels both extremely low and extremely high, to test whether the system
can deduce the correct changes to the power levels.
7.3 Integration/Regression Tests
What do the integration/regression testers need to do in order to test this MR.
Software Group will add this section
Signatures
| APPROVED |
To the best of my knowledge, the request in this MR is complete. I have thought through this request, and believe it to be an important feature to implement or bug to fix. |
| ACCEPTED |
I acknowledge that I have validated the completed code according to the acceptance tests. |
| Written |
- Glen Langston - 2009 September 15 |
| Checked |
- name - date |
| Approved by Sponsor |
- name - date |
| Approved by CCC |
- name - date |
| Accepted/Delivered by Sponsor |
- name - date |
Symbols: Use %X% if MR is not complete (will display
)
Use %Y% if MR is complete (will display
)
CCC Discussion Area--
-- GlenLangston - 2009-09-15