This project book is the home page for the 3rd generation USNO correlator build.

USNO 3rd Generation DiFX Correlator Project Book

A. Project Vision

To implement a new 3rd Generation 25 node DiFX correlator cluster at USNO DC and a new 2 node DiFX correlator prototype/test cluster at
Socorro NM.

B. Progress Indicators

Indicator Status Date 03/27/2024
Percent of Schedule Used 69% (11 of 16 months)
Percent of Budget Used (Actual / Planned)
Percent of Effort Used (Actual / Planned)
Last SOW Milestone Achieved MS2 "Assemble and Test In Socorro - Hardware"

C. Project Tracking

  • Current Task List
  • Current Issues
  • Status Reports
  • Project Log

D. Project Planning

  • Statement of Work
  • Stakeholder Requirements Enumeration
  • SOW Milestones Definitions
  • SharePoint
  • Microsoft Project File

E. Procurement Tracking

E.1. Procurement Planning

  • Estimated Hardware List to Complete
  • Advanced HPC

E.2. Procurement Log

Date Description Requsition PO Status
2023-05-30 BeeGFS 380135 Assembled
2023-07-28 Gigabit Switch 380803 Assembled
2023-07-28 InfiniBand Switch 308814 Assembled
2023-08-15 Admin Server, VM Host 380995 Assembled
2023-08-15 Compute Node 380994 Assembled
2023-08-24 InfiniBand Adapter, Cables 381070 Installed, Stored
2024-01-16 Rack 192355 Assembled
2024-01-23 PDU 192476 382436 Assembled
2024-02-09 SSD 382674 Installed

F. Technical Work Products

F.1. Technical Notes Exchanged with USNO

Doc ID Title Date Status
TN-815-001-A Hardware Architecture 2024-02-05 USNO general approval
TN-815-002-B Hardware Assembly Model - Rack Elevations 2024-02-06 Need revision with power utilization (Thomas working with Phillip)
TN-815-003-B Make Model Serial Number 2024-01-22 NRAO awaiting USNO 'graylist' verification
TN-815-004-B Shipping Dimensions 2024-01-24 USNO has responded that adequate receiving space is available
TN-815-005-B Network Architecture 2024-02-16 Needs revision with additional info (Thomas working with TJ)

F.2. Designs, Manuals, Guides and References

F.3. Tools and Software Repository

  • NetBox (online database application for inventory, DCIM, IPAM)
  • GitLab

F.4.Integration, Testing and Deployment

F.5. Security, Information Assurance, Risk Management Framework

  • Credentials - CAC
  • Greenfield Laptops
  • Scans
  • Checklists

G. Project Deliverables

G.1. SOW Status Reporting

815-USNO V3CorrRefresh-ProgressReport 2023-Dec
next quarterly

G.2. SOW Milestone Reporting

Doc ID Title Date
RPT-815-MS2-001-A Milestone MS2 Report 2024-03-20
RPT-815-MS2-002-A Milestone MS2 Hardware Acceptance Test Report 2024-03-20
RPT-815-MS2-003-A Milestone MS2 Hardware Inventory at Socorro 2024-03-20

-- ThomasColeman - 2024-03-27


When adding topics to this wiki make sure that "More topic actions" -> "Edit topic preference settings" contains:

   * Set ALLOWTOPICVIEW = Main.KnownNRAOWikiGroup

This is necessary to restrict access to authenticated NRAO users.


Topic revision: r4 - 2024-03-28, ThomasColeman