July 12th 11am MDT/1pm EDT

USNO Attendees: Nicole, Alan, Ken, Dave Boboltz, Dave Hall, John, Chris

NRAO Attendees: Kscott, Jeff, James, Walter, John

Agenda

  • Budget and Production cluster
    • Check on invoices
    • Production order deliveries complete
    • Several minor issues
      • 10gbit Fiber card availability
      • Original Cisco switch was untraceable restock from China, since replaced.
  • Schedule
    • Back on original schedule
    • Production cluster should be assembled by July 13th and fully functional by first week of August as planned
    • Walter to visit USNO July 18th to 20th
  • Last meeting items
    • NRAO to send power and heat load estimate to USNO
      • Concerned about 240v 20amp circuits and new high end node current draw, may need 4th circuit.
      • Quick/dirty calculation, 35 nodes at 250W = 8750W = ~30K BTU = 2.5 Tons cooling (note assumes 110V power).
    • USNO will send any Security policies we need to accommodate
      • May need to sign some paper work for ssh access
      • USNO Meeting with local IT, should know final answers next week
    • USNO to send floor plan
  • DiFX install script
    • Go over concepts, choices
    • NRAO to ship IPP licenses shipped to USNO

Discussion

  • Shipping logistics
    • Cluster will be shipped wired but with compute nodes removed.
    • Targetting first week of September, James to arrive just after cluster for re-assembly
  • Networking
    • Need specific addresses ranges in 10.1.33.0/24 space and 10.1.35/0/24 space DONE
    • Need specific addresses in 198.116.24.0/24 space
    • For the internal 10.1.34.0/24 space is it ok if we make a dummy DNS domain
      • USNO to be authorative
    • NRAO to send router rule needs
    • Mark5's will mount /home/difx from infrastructure nodes over gbit network
    • Need to order QSFP to SFP (1 to 4) break out cable for SAN-1 to Difx connection, 5meter limit
      • NRAO to order both
    • External access to secondary devices may be needed
  • Miscellaneous
    • What timezone should the servers be set for ? UTC, ET or other.
      • Use eastern time
  • Phase II discussion while Walter at USNO

-- JamesRobnett - 2012-07-09