July 12th 11am MDT/1pm EDT
USNO Attendees: Nicole, Alan, Ken, Dave Boboltz, Dave Hall, John, Chris
NRAO Attendees: Kscott, Jeff, James, Walter, John
Agenda
- Budget and Production cluster
- Check on invoices
- Production order deliveries complete
- Several minor issues
- 10gbit Fiber card availability
- Original Cisco switch was untraceable restock from China, since replaced.
- Schedule
- Back on original schedule
- Production cluster should be assembled by July 13th and fully functional by first week of August as planned
- Walter to visit USNO July 18th to 20th
- Last meeting items
- NRAO to send power and heat load estimate to USNO
- Concerned about 240v 20amp circuits and new high end node current draw, may need 4th circuit.
- Quick/dirty calculation, 35 nodes at 250W = 8750W = ~30K BTU = 2.5 Tons cooling (note assumes 110V power).
- USNO will send any Security policies we need to accommodate
- May need to sign some paper work for ssh access
- USNO Meeting with local IT, should know final answers next week
- USNO to send floor plan
- DiFX install script
- Go over concepts, choices
- NRAO to ship IPP licenses shipped to USNO
Discussion
- Shipping logistics
- Cluster will be shipped wired but with compute nodes removed.
- Targetting first week of September, James to arrive just after cluster for re-assembly
- Networking
- Need specific addresses ranges in 10.1.33.0/24 space and 10.1.35/0/24 space DONE
- Need specific addresses in 198.116.24.0/24 space
- For the internal 10.1.34.0/24 space is it ok if we make a dummy DNS domain
- NRAO to send router rule needs
- Mark5's will mount /home/difx from infrastructure nodes over gbit network
- Need to order QSFP to SFP (1 to 4) break out cable for SAN-1 to Difx connection, 5meter limit
- External access to secondary devices may be needed
- Miscellaneous
- What timezone should the servers be set for ? UTC, ET or other.
- Phase II discussion while Walter at USNO
--