June 14th 11am MDT/1pm EDT

USNO Attendees: David, Nicole, John Spitzak, Chris, Dave Hall

NRAO Attendees: John, Kscott, Walter, James

Agenda

  • Budget and Production cluster
    • Production orders under way
      • 33 2.9GHz Sandy Bridge processor nodes (head node plus 32 compute nodes
    • Slight hit on budget from faster processors and 10gbit SFP based switch
    • 120 day lead time on 10gbit cards, replacing with identical dual port card
  • Schedule
    • Benchmarks were completed by end of May, suggested 2.9Ghz processors to meet eventual Phase II requirements
    • Roughly 1 week behind schedule, originally planned to have orders complete by June 8th now looking like June 15th
      • Shouldn't pose a problem, sufficient slack in July and August to make up time
    • Production cluster should be assembled by July 13th and fully functional by first week of August
    • Walter to visit USNO July 18th to 20th
  • USNO Visit Last week of May if possible (Week of May 29th-June2nd) Wed 30th
    • Discussions on benchmark results and their meaning for Phase I and eventual Phase II
    • Discussion on network details, particularly 10gbit interconnects between correlator and existing SAN plus Mark5Cs
    • Discussion on Difx software installation scripts and procedures (including USNO adoption locally)
    • Local tests of USNO GUIs
  • Last meeting items
    • NRAO to send power and heat load estimate to USNO
      • Will revise rough estimates once we have 220V system in place
      • Quick/dirty calculation, 35 nodes at 250W = 8750W = ~30K BTU = 2.5 Tons cooling (note assumes 110V power).
    • USNO will send any Security policies we need to accommodate
      • May need to pull updates rather than push
      • May need to sign some paper work for ssh access
    • USNO to send floor plan

Discussion

  • Shipping logistics
    • We can pack and ship the rack fully loaded, will weigh about 1600Lbs. Can we actually handle the delivery end
    • Maybe we should just plan on breaking down the correlator into the rack plus 4 packs or 9 to 10 nodes. (still would weigh 200lbs so requires a floor dolly)
  • Documentation
  • Networking
    • Drawing will be ready by meeting
    • Mark5's will mount /home/difx from infrastructure nodes over gbit network
    • USNO to send SAN and public network drawing

-- JamesRobnett - 2012-06-12