USNO Difx Correlator kick off meeting

April 5th 1pm MDT/3pm EDT

USNO Attendees: Ken, Kerry, Nancy, Dave, Alan, Nicole, Chris

NRAO Attendees: Walter, Steve, James, Kscott

Agenda

  • Introductions
  • Describe and agree on monthly meetings (strawman below, doesn't apply for kick off meeting)
    • Report on work since last meeting
    • Work to be done in next month
    • Budget status
    • Open issues
  • Coordination
    • Project book pointer
    • Mailing list (external mailing list send wiki sign up)
    • Other ?
  • Present project schedule
    • Potential need for early visit in May to check off on test cluster
      • Late May seems preferable
    • Need to begin orders Monday if possible
  • Plan for initial test cluster
    • Small prototype cluster
    • 10gbit switch
    • 2 Mark5s
  • Miscellaneous details if time permits
    • Brief description of cluster architecture
    • RHEL 6.x
    • Network Addressing (mirror USNO addressing via bridged test rack network)

  • USNO SAN connectivity

Discussion

  • Continue with monthly meetings first Thursday of every month
  • NRAO to set up mailing list and send WIKI access instructions
  • General agreement to a late May USNO visit to Socorro to examine prototype cluster
  • NRAO to send power and heat load estimate to USNO
  • USNO to send likely IP ranges for final cluster, NRAO will use for test cluster
  • Make 10gbit network be fiber rather than UTP
  • USNO to send Mark5 10gbit connector type which drives switch SFP+ module selection
  • SAN could connect either directly to correlator switch or to a seperate switch with bonded interconnect to correlator switch
  • Correlator nodes are planned to be dual processor 8 core (16 total cores) but final decision will await test cluster
  • USNO will send any Security policies we need to accommodate
  • Walter and others may visit USNO this summer to take a look at existing GUI's
  • Question about contract requirement inspection of supplies record keeping
    • What form do those records take and how long do we keep them
    • USNO to answer above
  • We'll try and use video conferencing next time
  • Discussion of Mark5 unit support
    • We can distribute Difx software to them from correlator support nodes
    • OS support may be beyond the scope of the project and not really necessary.
    • NRAO will look at cross compiling 32bit Difx

-- JamesRobnett - 2012-04-04