Casa Parallelization meeting minutes

Monday February 6th Room 317, 3:30pm MDT

Attendees:

Targets/tasks for January 6th - February 13th

Discussion/Agenda

  • Update on Partitioning status (null selections, non-conforming tasks) Jeff
  • Update on asdm2ms_xl schedule for stable inclusion
    • Does not handle large syspower tables
    • Still serial, eventually multi-threaded across spw, multi-process across scans
  • Model data tests
    • No benchmarking done last week James
  • Begin re-examination of multithreaded gridder
  • Pcube and pclean as task after model data work Kumar
  • Lustre file I/O failure Jim/James
    • Need to test whether it's actually fixed
  • Revisit async iterator for writing Jim/Justo
    • Refactoring seems to be working in active
    • Justo is testing flagging
    • Pointer rewrite in active
  • Memory resident subtables Jim
    • Recent tests with storage manager inconclusive, James needs to retest
      • Check that it affects number of FDs as well
    • flagging infrastructure most likely next target (Justo might do)
    • Partition worth looking at
  • Spectral imaging Kumar
    • Understand channel chunk choice effect on memory James
  • Need 400+GB continuum case with complex field
    • Stalled for partitioning

CASA HPC Initiatives for the 3.4 Cycle

  • Memory Footprint Issues
    • Deployment of Multi-Field MS-MFS (Urvashi) Deferred
    • Deployment of Parallel Gridder and splitting of the Grid (Jim)
    • Design of MS-MFS Minor Cycle Parallelization (Jim et. al.) using Friday meetings Deferred
  • Initial Deployment of ASP Clean (Sanjay)
  • Performance Issues:
    • Virtual Model Data Column (Kumar) Done
      • Removes model data column
      • removes need for Setjy
    • Memory Resident Subtables Deployment In progress needs testing
    • VisBuffer Processing Framework
      • Add Write capability (Jim) Need to revisit but seems to work in not imaging
      • Deployment in tasks (Jeff to Assign)
    • Parallel Filler (and partitioning) (Tak) In progress
  • User Interface:
    • Parallel Imager in Task (Kumar)
    • Parallelization of other Tasks (assigned to Europe)

Deferred Topics

ARDG Targets

  • What is negative side effect of CVel in filler, non-reversible
  • What needs to be done to acceptably implement Auto-boxing with large number of channels

-- JamesRobnett - 2012-02-27
Topic revision: r1 - 2012-02-27, JamesRobnett
This site is powered by FoswikiCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding NRAO Public Wiki? Send feedback