VEGAS Team Meeting

GB-137-hub
192.33.117.12##7144
434-817-6443# (telephone)

Attendees: Ray, Adam, Joe, Sam, Paul, Marty, Jason, John, Richard, Randy

Agenda:

  1. Baseline tests, results and actions
  2. 'Spike' tests, results and actions
  3. Test Time

Meeting notes:

  1. Baseline tests, results and actions
    • Anish to draft MR
  2. 'Spike' tests, results and actions
    • Latest from UCB/Jones
    • Next steps
      • Try the shift setting tests recommended (ffff v. aaaa)
        • test first on SRBS
        • The re-run on VEGAS
    • Recheck OGP(?) calibrations on the next maintenance day
    • First fix build environment (NRAO & UCB)
    • Then look for Mode 2&3 spikes/fix spikes
    • Then look at spikes in Mode 4 (believe problem is different)
  3. Test Time
    • Wednesday
      • OGP calibrations (~8a) [Ray/Marganian]
      • Time sample series for Mode 4 and compare with Mode 2 & 3 to see if there is correlation
      • IF passband into ADC for Modes 1,2,& 3 [Watts]
    • Thursday
      • Shift Setting tests (10a) [Brandt/Kobelski]
    • Test on SRBS
      • shift setting tests (ffff v. aaaa) [Brandt]
  4. Other
    • Mode 19 (L8)- tests were not successful, may use SRBS as test bed for further development & test

-- MartyBloss - 2014-09-02

This topic: CICADA > WebHome > GreenBankSpectrometer > CICADAVegasProjectMeetings > VEGASTeamMeeting02September2014
Topic revision: 2014-09-02, MartyBloss
This site is powered by FoswikiCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding NRAO Public Wiki? Send feedback