VEGAS Team Meeting
Attendees: Richard, Marty, Dan, Mark W., Joe, Ray, Jason, Randy
Agenda:
- Status update on IFNUM testing
- Status update on DIBAS standalone manager work
- Status of ADC Calibration -- Dan W.
- review of schedule
- plans for testing for this week
Meeting notes:
- Status update on IFNUM testing
- Tests and corrections next week will finish testing, but now a week behind schedule.
- Status update on DIBAS standalone manager work
- Some L1 tests opened some issues
- probably re-test L1 - L8 tomorrow afternoon
- Status of ADC Calibration -- Dan W.
- Hong has been preempted by other work, but will work on this next week. Someone can handle running the scripts here in GB with Hong's assistance.
- Probably a combination of Jason and a s/w engineer
- creates a correction factor (phase & gain) as a function
- needs to be loaded into the ADCs upon startup via 'listdev' but needs some documentation on the registers that would hold the correction factors
- review of schedule
- modes 20-29 are dependent on IFNUM
- Amanda is available for tests on GBT this week
- DIBAS testing starts this week and should start tomorrow so we are probably ok.
- plans for testing for this week
- Other
--
MartyBloss - 2014-01-27