VEGAS Team Meeting
Attendees: Anish, Amanda, Glenn, Dan, Mark Whitehead, Randy, Joe, John.
Agenda:
Progress and status of FPGA personalities
Mode 1 (h1k)
OK, except for 1/16th band issues. Glenn and Andrew Maartens working on it.
Mode 2/3 (h16k)
OK, except for 1/16th band issues. Glenn and Andrew Maartens working on it.
Mode 20-29 (l8)
Ready to start testing today with standalone systems\ when compile finishes. Will prioritize h1k and h16k fixes where appropriate.
Mode 10-19 (l8)
No FPGA work on this mode if 20-29 is OK
Mode 4-9 (l1)
Ready for Manager testing. Joe will test it out later this week or early next week.
Status of NRAO software
Mode 1
- Original ready to go
- Refactored version lightly tested by Ray, but not released yet. Next week it will be released after a bit more testing.
Mode 2
- Original ready to go
- Refactored version lightly tested by Ray, but not released yet. Next week it will be released after a bit more testing.
Mode 3
- Original ready to go
- Refactored version lightly tested by Ray, but not released yet. Next week it will be released after a bit more testing.
Mode 20-29
- Refactored version lightly tested by Ray, but not released yet. Next week it will be released after a bit more testing.
Mode 10-19
Mode 4-9
- Refactored version lightly tested by Joe.
Other work in progress:
- Testing/work on switching signal anomalies -- Joe thinks this is fixed, but needs to be tested.
- Mode documentation -- Joe is happy with Glenn's additions, and Glenn will be adding more in the next week or so.
Proposed final schedule
- Mode 1-3 finished first
- Released to final testing 12/6/2013
- Mode 20-29 next
- Released to final testing 12/19/2013
- Mode 10-19 next
- Released to final testing 1/28/2014
- Mode 4-9 next
- Released to final testing 3/11/2014