M&C portion of MR may be ready for deployment by next week
Improve the reliability of MMCM calibration (as Jack suggested).
Implement MMCM calibration each time bof is reloaded.
Weekly testing schedule
Tuesday (all day)
8:30am - 11:00am [Priority 1] Test time to confirm 'Frequency Switching' problem (consult w/Anish for the kind of data he would want) - Brandt/Kepley
1:30pm - 4:30pm [Priority 2] Test time for a series of Mode #4 data collection for the composite view of the different parameters used. Many short scans more useful than few long scans (60 sec w/multiple integrations per scan). - Kepley
Thursday (likely afternoon) * Subreflector testing Thursday 2:00 4:00pm - Prestage. (Doesn't prevent VEGAS testing, but well need to coordinate with any VEGAS testing)
Missing channels testing w/Jayanth (if not Tuesday
Please make sure to properly code your timesheets for the current time period and going forward.
Software engineers should be using a GBT ops software CM&E account - Account 893252
Electronic engineers should be using a GBT ops electronics CM&E account - Account 432510
Commissioning activities should be getting charged to hardware support and testing - Account 432510
Scientists assisting with shared-risk commissioning should be charging an observer support account
432540 for the most part. Accounts 142020 (GB-based staff) and 142010 (CV-based staff) for when you are helping with overarching observing support (not problem solving, VEGAS specific)