Goal Original Milestone Revised Milestone Comments
First version of the iBob and ADC modules produced and documented 06/01/07 06/28/07 Complete DONE
Next Generation EXPERT User NRAO Pulsar Backend including: dual polarization, detected power, “Lite RPC Server”, and test / demonstrator data collection machine (scaled down) 30 Nov, 2007 30 Jan 2008  
Next Generation EXPERT User NRAO Pulsar Backend, including PSRFITS formatter and full stokes parameters 31 Dec, 2008 29 Feb 2008  
Complete specifications for Phase 2 01 Jan, 2008 01 Mar, 2008  
Next Generation Pulsar Machine Phase 1 (Spigot Replacement) 01 Jan, 2008 01 Mar, 2008  
_Prototype and design coherent dedispersion modes 01 Apr, 2008    
Next Generation EXPERT User NRAO Pulsar Backend (same as 1.6 with coherent dedispersion added) 15 Feb, 2008 01 Jun, 2008  
Next Generation EXPERT User NRAO Pulsar Backend (same as 1.7 with pulsar period folding added) 30 Jun, 2008 01 Jul, 2008  
Next Generation Pulsar Machine Phase 2 (Coherent Machine) 30 Jun, 2008 30 Aug 2008  
Next Generation Pulsar Machine Phase 3 (Common User Machine) 30 Jun, 2009 30 Aug 2009  
Design Study for Array Spectrometer 30 Sept 2008    