VEGAS / DIBAS Weekly Review Meeting - 2013 october 02

Connection Details:

Green Bank GB-Basement Video: 192.33.117.12##7145 Audio: 434-817-6459

Present

  • Richard, Marty. Mike

DIBAS Status

  • DIBAS commissioning preparation is going well.
  • On-site acceptance and commissioning to start next week (October 7th)
  • All pulsar modes will be available, spectral line modes 1-3.

VEGAS Status

  • Software work has been diverted to DIBAS commissioning preparation.
  • Engineering tests of mode 4 were completed last week. A problem with ripple in the baseline appears to have been fixed; this will be confirmed next week.
  • Anish and Glenn Jones will continue engineering tests of modes 6 and up, without software assistance.

SHAO communications status

  • No updates.

-- RichardPrestage - 2013-09-10
Topic revision: r4 - 2013-10-22, RichardPrestage
This site is powered by FoswikiCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding NRAO Public Wiki? Send feedback