VEGAS / DIBAS Weekly Review Meeting - 2013 August 28
Connection Details:
Green Bank GB-Basement Video: 192.33.117.12##7145 Audio: 434-817-6459
Present
DIBAS Status
VEGAS Status
Present
Richard, Lory, Karen, Marty, Mike
DIBAS Status
Hardware on route to Shanghai, eta at airport August 28, at 11:50 AM.
DIBAS cost discussed in a separate document - Lory will arrange a meeting with Laura to review the budget
RMP informed SHAO of the specification change for coherent search mode - no response as yet.
VEGAS Status
The Mode 1 test report has been received; Mode 1 passes all the tests.
The software for Modes 4 through 9 has been completed. We will do engineering tests today and tomorrow, and astronomical tests over the weekend.
A revised test plan schedule is attached to the main wiki page
--
RichardPrestage
- 2013-08-26
This topic: CICADA
>
WebHome
>
GreenBankSpectrometer
>
CICADAGreenBankSpectrometerAug2013TestPlan
>
CICADAGreenBankSpectrometerStatus2013Aug28
Topic revision:
2013-08-28,
RichardPrestage
Copyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding NRAO Public Wiki?
Send feedback