VEGAS / DIBAS Weekly Review Meeting - 2013 August 28

Connection Details:

Green Bank GB-Basement Video: 192.33.117.12##7145 Audio: 434-817-6459

Present

  • Richard, Lory, Karen, Marty, Mike

DIBAS Status

  • Hardware on route to Shanghai, eta at airport August 28, at 11:50 AM.
  • DIBAS cost discussed in a separate document - Lory will arrange a meeting with Laura to review the budget
  • RMP informed SHAO of the specification change for coherent search mode - no response as yet.

VEGAS Status

  • The Mode 1 test report has been received; Mode 1 passes all the tests.
  • The software for Modes 4 through 9 has been completed. We will do engineering tests today and tomorrow, and astronomical tests over the weekend.
  • A revised test plan schedule is attached to the main wiki page

-- RichardPrestage - 2013-08-26

This topic: CICADA > WebHome > GreenBankSpectrometer > CICADAGreenBankSpectrometerAug2013TestPlan > CICADAGreenBankSpectrometerStatus2013Aug28
Topic revision: 2013-08-28, RichardPrestage
This site is powered by FoswikiCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding NRAO Public Wiki? Send feedback