Tests for March 2012

Objective

  • System to conduct pulsar observations
  • Test data delivery into the NRAO servers
  • Test switching signals with Mode #1

To-do list to accomplish these objectives

Hardware (Assigned to Jason with Galen responsible for the IF items)

Rack layout drawing here: March 2012 Test Rack Layout

Rack block diagram sheet 1 of 3 here: March 2012 Test Rack Block Diagram SH1

Rack block diagram sheet 2 of 3 here: March 2012 Test Rack Block Diagram SH2

Rack block diagram sheet 3 of 3 here: March 2012 Test Rack Block Diagram SH3

03/14/12 -- Status updates embedded below in red (JMR)
  • DONE Configure our other 2 roaches so that they boot up like roach1 and roach3 does
  • DONE Re-name the roaches to vegas-r1 through vegas-r8
  • DONE Configure the Cal Tech roaches so that they boot up in our system.
  • DONE Setup static IPs for all 8 roaches.
  • DONE Build & test Valon RFI boxes
  • DONE Add Valons to each roach
    • DONE We'll need to round up/buy six more power dividers to split the clk between the two ADC's per roach
    • DONE Number of machines to use and their serial connections
      • DONE North, South, East, West, Cicada2, Quail, 43m-ctl, Trigger
      • DONE Each machine will have a serial port.
    • DONE If we have a Valon in each roach, we need to figure out where to connect them serially. And, buy more serial cables.
  • DONE Mount the roaches in the rack
  • DONE Might need to reconfigure the current rack layout so that eight roaches and IF modules actually fit..?
  • DONE Build up cabling between the ADC's, Valons, etc. Galen is working on the IF-to-ADC part of this.
  • DONE Build up six more BNC cables for 1PPS to each roach
  • DONE Build up six more flat cables for switching signals to the other roaches
  • DONE Round up additional 10GbE cables (I think Dan volunteered to bring these)
  • DONE Cabling for the I2C connections from each roach.
    • DONE Part of each IF module power supply harness.
  • DONE Install splitter for 10MHz dist to each roach (Galen already gave me the splitter)
  • DONE Round up additional twisted pair cables for the roaches 100Mb network
  • DONE Add more capacity to the private network section
  • DONE Upgrade motherboards in north, south, east, west.
  • DONE Build up rack of eight computers and the UPS.
  • DONE AC power connection in the equipment room for computer rack and roach/IF rack.
    • DONE Two 3-phase 30A outlets under the floor in the correct area
      • DONE Get works area to re-wire for single phase 120V
    • DONE Build up one ganged outlet box with 30A twist lock plug for the roach/IF rack.
    • DONE Obtain/build two floor tiles with holes in them
  • UC-B will bring to the test -
    • DONE ADC Boards
    • DONE 10 GbE cables

Software (Refer to project meeting notes)

Firmware (DSP designs from Berkeley)

Put your content here, and don't forget to sign!

Pulsar observations for the GC, March 2012

Topic revision: r24 - 2012-07-24, JasonRay
This site is powered by FoswikiCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding NRAO Public Wiki? Send feedback