2007-02-08 ALMA Calibration Group Telecon Agenda and Minutes


ALMA Calibration Group Telecon
  • Date: February 8, 2007 (Thursday)
  • Time: 15:00 UT
  • Duration: 1.0 hr
  • USA Toll Free Number: 1-877-919-7148
  • International: +1-203-566-1039
  • Passcode: 5 1 0 4 6 8
  • Leader: JeffMangum

Table of Contents:



Complete List of Action Items


Action Items from Last Telecon

Assigned To Due Date Description State Notify  


Agenda and Minutes

NOTE: Discussion from the telecon is shown in italic.


Attendees

  1. MarkHoldaway
  2. JeffMangum
  3. Sakiuchi
  4. BaltasarVilaVilaro


Calibration Examples Status

Still waiting on final versions of bandpass (RobertLucas), delay (RobertLucas), polarization (EdFomalont), optics (BaltasarVilaVilaro), and ACA calibration issues (BaltasarVilaVilaro) calibration examples. See CalExamples wiki for further information.


Calibration Sequence Development

Will begin process of turning CalExamples into calibration "sequences" during 2007Q1. Need to first meet with Computing IPT to figure out which Computing IPT personnel will be available to participate in sequence development.


Amplitude Calibration Subsystem Development Reports

  • Berkeley Absolute Flux Calibration System (Jack Welch)
    • No report.
  • Semi-Transparent Vane (STV) Calibration System
    • Need only to get final report from Jesus Martin-Pintado. This is still pending.
  • Multi/Dual-Load (M/DL) Calibration System (Matt Carter)
    • No new news.


Weather (Ancilliary) Measurement Devices

In December 2006 JeffMangum submitted weather station instrumentation (RH, P, T, and wind) RFQ documentation to NRAO procurement system. Procurement back in JGM's hands now. After having reviewed information received from bidders, JeffMangum wonders if it would be more effective to purchase slightly less capable (P,T,RH) but cheaper measurement systems, and to buy more of them to better sample the (P,T,RH) conditions over the ALMA site. Consensus was that this was a good idea. JeffMangum will get detailed information on recommended instrumentation and post to this group.


Allocation of Weather Devices for the OSF

AlWootten notes that the Science IPT needs to provide a plan, with AIV, for weather station installation at the OSF within the next month or two. At the AOS near the TB in the ESO trailer is a Davis weather station. There is another weather station on a tower near the APEX site, according to Nyman. Neither is currently being used. These could be moved to the holography tower at the OSF.

There are two CR4 hygrometers in the US. One is under repair at the manufacturer (Buck Research) under a contract with ESO and will be returned to Tucson and Angel shortly. Another, at the ATF, is reportedly nonfunctional. The repaired instrument may be installed at the OSF.


Solar Observations and Calibration

MarkHoldaway has written a draft document on Calibration of Solar Observations. We discussed this document at our last telecon. Few revisions are needed. MarkHoldaway will update and submit final version within the coming few weeks.


Date of Next Phone Meeting

The next ALMA Calibration Group telecon will be 2007, March 8th 15:00 UT.
-- JeffMangum - 08 Feb 2007
Topic revision: r2 - 2007-02-08, JeffMangum
This site is powered by FoswikiCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding NRAO Public Wiki? Send feedback